This is not a substitute for legal advice.  An attorney must be consulted.

"This work is protected under the copyright laws of the United States.  No reproduction, use, or disclosure of this work shall be permitted without the prior express written authorization of the copyright owner.  Copyright © 1994 - 2015 by LAWCHEK, LTD."

BACK TO MAIN  MENU

 

DEADLINE EXTENSION AMENDMENT

          The parties in authority as identified below hereby agree to amend the subcontractor performance agreement for residential construction:
          a) 15 Bad Weather Days that are identified in paragraph 6 of the subcontractor performance agreement that have already occurred are:

Day of Week Date Owner/Contractor
Initials
Subcontractor
Initials
  1.  

  2.  

  3.  

  4.  

  5.  

  6.  

  7.  

  8.  

  9.  

  10.  

  11.  

  12.  

  13.  

  14.  

  15.  

Monday1 8/12/961 ________1 ________1

          b) The total of 12 additional days will be permitted as an extension to the deadlines set forth in paragraph 4 of the subcontractor performance agreement before liquidated damages (paragraph 5 of said contract) are imposed.

          Dated at Rockland, Idaho3 on this 13th day of August, yr19964.

 

                                        5                                         6
Owner/Contractor Subcontractor

 

This is not a substitute for legal advice.  An attorney must be consulted.
Copyright © 1994 - 2015 by LAWCHEK, LTD.

The form above is an example of how a typical Deadline Extension Amendment form may be completed.

  1. The purpose of a Deadline Extension Amendment is to allow the flexibility for additional bad weather days, etc., which may be encountered by a contractor.  In this particular case, there was only one exception allowed for one such day, which would give the contractor an additional day beyond his deadline of the original agreement.  If the reader will look back to the Subcontractor Performance Agreement, the reader will note that there is a provision in Paragraph 6 for weather days and in Paragraph 5 for liquidated damages.  Generally, a Deadline Extension Amendment would allow the contractor additional days beyond the deadline, thereby eliminating liquidated damages on the days for which exceptions were allowed.

  2. Only 1 additional day was hypothetically noted in this case.

  3. The location where the Deadline Extension Amendment is signed should be noted.  In this case, a hypothetical city was used.

  4. The date the agreement is signed should be noted.

  5. The signature of the owner/contractor.

  6. The signature of the subcontractor.

This is not a substitute for legal advice.  An attorney must be consulted.
Copyright © 1994 - 2015 by LAWCHEK, LTD.

BACK TO MAIN  MENU

 

This is not a substitute for legal advice. An attorney must be consulted.